Namalco Construction Services Ltd v Estate Management & Business Development Company Ltd
Jurisdiction | Trinidad & Tobago |
Judge | Mr. Justice R. Rahim |
Judgment Date | 26 April 2022 |
Neutral Citation | TT 2022 HC 087 |
Docket Number | Claim No.: CV2016-01522 |
Court | High Court (Trinidad and Tobago) |
(By Original Action)
and
and
and
(By Ancillary Claim)
the Honourable Mr. Justice R. Rahim
Claim No.: CV2016-01522
IN THE HIGH COURT OF JUSTICE
Claimant: Mr. A. Fitzpatrick SC, Mr. S. Sharma and Mr. R. Kawalsingh instructed by Mr. J. Mohammed.
Defendant/Ancillary Claimant: Mr. J. A. Davis QC, Mr. G. Hayman QC and Mr. C. Kangaloo instructed by Ms. D. Nieves-Inglefield
First Ancillary Defendant: Ms. J. Lutchmedial.
Second Ancillary Defendant: Mr. D. Mendes SC, Mr. D. Maharaj and Mr. C. Hackett instructed by Ms. K. Bharat.
Third Ancillary Defendant: absent and unrepresented.
Fourth Ancillary Defendant: Mr. A. Singh.
Introduction | 9 |
Overview | 9 |
Disposition of the Claim and Counterclaim | 15 |
The Claim and Counterclaim | 17 |
Issues | 18 |
The Claim | 21 |
Issue 1 — Whether the court has the jurisdiction to hear challenges to the validity and accuracy of the IPCs | 21 |
The FIDIC terms of contract | 21 |
Preliminary issue: Should Namalco be permitted to argue that the court lacks jurisdiction to hear challenges to the validity and accuracy of the IPCs | 27 |
The main issue on Jurisdiction | 27 |
Findings | 35 |
Are the requirements set out in the DRP prerequisites to challenging the IPCs in court or put another way, does the fact that the DRP process was not engaged by a party prohibit that party from challenging the IPC in court | 38 |
Cedar Hill and Petit Morne | 41 |
Roopsingh Road and Picton Contracts | 42 |
Issue 2 — What was the effect of Clause 2.5 of the Conditions of Contract on EMBD's defence and counterclaim | 43 |
All Contracts | 43 |
Finding | 49 |
Abatement and the alleged extinguishment of Namalco's claim | 50 |
Issue 3 — Whether the provision of supporting documents was a condition precedent to the payment of an IPC | 51 |
Findings | 65 |
Issue 4 — Whether the decision of the Dispute Adjudication Board on the Picton Contract has become conclusive | 74 |
Findings | 76 |
Issue 5 — Whether the supplementary agreements are valid | 78 |
The Roopsingh Road Project | 78 |
he Petit Morne Project | 79 |
Whether Mr. Singh procured or caused EMBD to enter into the Supplementary Agreements in breach of his statutory fiduciary duties and not in best interests of EMBD/preferring interests of Namalco and/or without actual authority to do so | 80 |
Whether Namalco knew that Mr. Singh acted not in the best interests of EMBD/preferring the interests of Namalco, and was thereby acting in breach of his Statutory Fiduciary Duties, and/or without actual authority | 82 |
Whether it can be inferred in all the circumstances that Namalco and Mr. Singh conspired together to procure the award of the Supplementary Agreements with an intention to injure or cause financial loss to EMBD by the use of unlawful means (namely Mr. Singh's breaches of fiduciary duties procured by Namalco) | 83 |
Whether EMBD's purported ratification of the Supplementary Agreements is of no effect, by reason of EMBD not knowing (i) that the Supplementary Agreements had been entered into in breach of Mr. Singh's fiduciary duties and/or without authority, and (ii) that Namalco knew this | 83 |
Whether EMBD has established on the evidence that Singh breached any of his duties or non-fiduciary duties | 85 |
Whether Namalco's Representatives were, in any event, aware of Singh's alleged breaches of his duties owed to EMBD | 86 |
Whether Singh had Apparent or Ostensible Authority to enter into the Supplementary Agreements on behalf of EMBD | 88 |
Finding | 89 |
Ostensible authority | 91 |
The Indoor Management Rule/Rule in Turquand | 97 |
Did Namalco have knowledge of the fact that Singh possessed no actual authority to enter into the Supplementary Agreements for a sum above $1M | 108 |
Should Namalco have been put on inquiry that Singh had no such authority | 109 |
Is the subsequent ratification by the Board valid and if so what is the effect on the validity of the supplementary contracts | 110 |
Breach of fiduciary duty | 115 |
Conspiracy | 117 |
The pleading point | 119 |
The evidence of conspiracy | 119 |
Discussion | 123 |
Agreement or combination between Namalco and EMBD and Others | 127 |
An intention to injure the party who alleged the conspiracy | 131 |
Unlawful acts carried out pursuant to the agreement and knowledge of unlawfulness | 132 |
Loss to the injured party as a consequence of the acts | 132 |
Issue 6 — What is the value of the works executed by Namalco | 133 |
The Picton project | 133 |
The other projects | 134 |
Defective Work: The Counterclaim | 134 |
Barrie Jones | 141 |
Report of Ioannis Barmpopoulos | 156 |
The Fugro Report | 157 |
Jonathan Palmer | 165 |
Namalco's Expert on Value/Rates | 170 |
Phillip Duggan | 170 |
EMBD's Experts | 173 |
Sarah Pattinson | 173 |
Mark Hood | 175 |
Discussion and findings | 175 |
Projects | 176 |
Roopsingh Road Value | 176 |
Clearing and grubbing or Stripping | 177 |
Preliminary Items for Office and Security | 177 |
Overheads | 178 |
Equipment | 178 |
Clearing and grubbing | 181 |
Imported sand fill | 182 |
Individual claims for excavation and imported sand fill | 182 |
Recovery of profit — omission of detention ponds | 183 |
Fill and re-grading | 183 |
Variations | 183 |
Petit Morne Value | 186 |
Cedar Hill Value | 186 |
Insurance and performance security | 186 |
Other Provisional sums | 188 |
Overheads resulting from the suspension of works | 190 |
Equipment | 191 |
Landslip | 192 |
Clearing and grubbing: IPC1 | 193 |
Embankment from borrow | 194 |
The Systemically Defective Nature of Namalco's Works — Defective Work — Bill Section C | 196 |
Interest | 197 |
The Ancillary Claim | 198 |
Disposition | 199 |
Costs | 201 |
Picton Project | 201 |
Cedar Hill Project | 202 |
Contractual obligations/breaches under common law duty | 209 |
Monthly progress reports | 212 |
Provisional sums | 221 |
Embankment from borrow | 222 |
Roopsingh Road Contract | 225 |
Provisional sums | 226 |
Equipment | 226 |
Recovery of profit — omission of detention ponds | 231 |
Fill and re-grading | 234 |
Variations | 235 |
Petit Morne Contract | 236 |
The Petit Morne Project calculations | 236 |
Sub-standard and defective works | 238 |
Overheads | 238 |
Equipment | 240 |
Wrongful variation to excavation widths | 241 |
Recovery of profit — omission of detention ponds | 242 |
Assessment of Interest | 242 |
AASHTO 180/191 | 242 |
The Counterclaim of APCL to the Ancillary Claim | 243 |
To say that this case has been somewhat of a challenge would be to underestimate the sheer volume of issues and sub-issues which have been raised. Contrary to the assertion of the Attorneys at Law for the Claimant that it was really a simple matter, its complexity has literally consumed a disproportionate amount of the court's time and resources despite the efforts of the court to minimise that occurrence. In that regard, the court has also intentionally refrained from setting out all of the evidence; as so to do would be to detract from what the court hopes the reader would find to be more interesting and comprehensible than burdensome. That is not to say that the court has not considered all of the evidence that was presented before it as it has. The court has, however, tried to keep the decision within the limits of the reasonable.
The nature of the case has presented considerable overlap between the Claim and the Ancillary Claim both in terms of facts and law. To that end, where an issue may not have been dealt with as fully as the court would have liked to treat with it in one area, it has more likely than not been dealt with in the other area. Additionally, having regard to the myriad of findings the court has attempted to make appropriate orders for relief as best suits the case. As with all judgments the longer it lives with the writer the more he wishes he could add to his writing but there comes a time when it must end and the judgment delivered.
The court wishes to add that rarely does a court mention the word “politics” in a judgment and for very good reasons, the most important of which is the preservation of the independence of the Judiciary. However, it will not escape the reader that these claims and those similar to them have been the subject of much speculation on all sides of the political fence if one is to accept that which is printed in the newspaper. The courts have never been and ought never to be involved in the business of politics so that the findings made herein are devoid of any such consideration for the absolute avoidance of doubt. It is necessary to remind our people of this steadfast principle from time to time in order to maintain the confidence reposed in the courts throughout our twin island Republic.
The Claimant (“Namalco”) and the Defendant (“EMBD”, a state enterprise) entered into contracts for six (6) construction projects at Mahaica, Brickfield, Cedar Hill, Roopsingh Road, Petit Morne and Picton Monkey Town under which Namalco was to perform infrastructural...
To continue reading
Request your trial