Namalco Construction Services Ltd v Estate Management & Business Development Company Ltd

JurisdictionTrinidad & Tobago
JudgeMr. Justice R. Rahim
Judgment Date26 April 2022
Neutral CitationTT 2022 HC 087
Docket NumberClaim No.: CV2016-01522
CourtHigh Court (Trinidad and Tobago)
Between
Namalco Construction Services Limited
Claimant
and
Estate Management & Business Development Company Limited
Defendant

(By Original Action)

And Between
Estate Management & Business Development Company Limited
Ancillary Claimant
and
Andrew Walker
First Ancillary Defendant

and

Atlantic Project Consultants Limited
Second Ancillary Defendant

and

BBFL Civil Limited
Third Ancillary Defendant

and

Lee Young and Partners (A Partnership and/or Firm registered under the laws of Trinidad and Tobago and issued pursuant to Section 12 of the Partnership Act Chapter 81:02 and in accordance with Part 22.1 of the Civil Proceedings Rules 1988, as amended)
Fourth Ancillary Defendant

(By Ancillary Claim)

Before

the Honourable Mr. Justice R. Rahim

Claim No.: CV2016-01522

IN THE HIGH COURT OF JUSTICE

Appearances:

Claimant: Mr. A. Fitzpatrick SC, Mr. S. Sharma and Mr. R. Kawalsingh instructed by Mr. J. Mohammed.

Defendant/Ancillary Claimant: Mr. J. A. Davis QC, Mr. G. Hayman QC and Mr. C. Kangaloo instructed by Ms. D. Nieves-Inglefield

First Ancillary Defendant: Ms. J. Lutchmedial.

Second Ancillary Defendant: Mr. D. Mendes SC, Mr. D. Maharaj and Mr. C. Hackett instructed by Ms. K. Bharat.

Third Ancillary Defendant: absent and unrepresented.

Fourth Ancillary Defendant: Mr. A. Singh.

TABLE OF CONTENTS

Introduction

9

Overview

9

SECTION ONE

Disposition of the Claim and Counterclaim

15

The Claim and Counterclaim

17

Issues

18

The Claim

21

Issue 1 — Whether the court has the jurisdiction to hear challenges to the validity and accuracy of the IPCs

21

The FIDIC terms of contract

21

Preliminary issue: Should Namalco be permitted to argue that the court lacks jurisdiction to hear challenges to the validity and accuracy of the IPCs

27

The main issue on Jurisdiction

27

Findings

35

Are the requirements set out in the DRP prerequisites to challenging the IPCs in court or put another way, does the fact that the DRP process was not engaged by a party prohibit that party from challenging the IPC in court

38

Cedar Hill and Petit Morne

41

Roopsingh Road and Picton Contracts

42

Issue 2 — What was the effect of Clause 2.5 of the Conditions of Contract on EMBD's defence and counterclaim

43

All Contracts

43

Finding

49

Abatement and the alleged extinguishment of Namalco's claim

50

Issue 3 — Whether the provision of supporting documents was a condition precedent to the payment of an IPC

51

Findings

65

Issue 4 — Whether the decision of the Dispute Adjudication Board on the Picton Contract has become conclusive

74

Findings

76

Issue 5 — Whether the supplementary agreements are valid

78

The Roopsingh Road Project

78

he Petit Morne Project

79

Whether Mr. Singh procured or caused EMBD to enter into the Supplementary Agreements in breach of his statutory fiduciary duties and not in best interests of EMBD/preferring interests of Namalco and/or without actual authority to do so

80

Whether Namalco knew that Mr. Singh acted not in the best interests of EMBD/preferring the interests of Namalco, and was thereby acting in breach of his Statutory Fiduciary Duties, and/or without actual authority

82

Whether it can be inferred in all the circumstances that Namalco and Mr. Singh conspired together to procure the award of the Supplementary Agreements with an intention to injure or cause financial loss to EMBD by the use of unlawful means (namely Mr. Singh's breaches of fiduciary duties procured by Namalco)

83

Whether EMBD's purported ratification of the Supplementary Agreements is of no effect, by reason of EMBD not knowing (i) that the Supplementary Agreements had been entered into in breach of Mr. Singh's fiduciary duties and/or without authority, and (ii) that Namalco knew this

83

Whether EMBD has established on the evidence that Singh breached any of his duties or non-fiduciary duties

85

Whether Namalco's Representatives were, in any event, aware of Singh's alleged breaches of his duties owed to EMBD

86

Whether Singh had Apparent or Ostensible Authority to enter into the Supplementary Agreements on behalf of EMBD

88

Finding

89

Ostensible authority

91

The Indoor Management Rule/Rule in Turquand

97

Did Namalco have knowledge of the fact that Singh possessed no actual authority to enter into the Supplementary Agreements for a sum above $1M

108

Should Namalco have been put on inquiry that Singh had no such authority

109

Is the subsequent ratification by the Board valid and if so what is the effect on the validity of the supplementary contracts

110

Breach of fiduciary duty

115

Conspiracy

117

The pleading point

119

The evidence of conspiracy

119

Discussion

123

Agreement or combination between Namalco and EMBD and Others

127

An intention to injure the party who alleged the conspiracy

131

Unlawful acts carried out pursuant to the agreement and knowledge of unlawfulness

132

Loss to the injured party as a consequence of the acts

132

Issue 6 — What is the value of the works executed by Namalco

133

The Picton project

133

The other projects

134

Defective Work: The Counterclaim

134

Barrie Jones

141

Report of Ioannis Barmpopoulos

156

The Fugro Report

157

Jonathan Palmer

165

Namalco's Expert on Value/Rates

170

Phillip Duggan

170

EMBD's Experts

173

Sarah Pattinson

173

Mark Hood

175

Discussion and findings

175

Projects

176

Roopsingh Road Value

176

Clearing and grubbing or Stripping

177

Preliminary Items for Office and Security

177

Overheads

178

Equipment

178

Clearing and grubbing

181

Imported sand fill

182

Individual claims for excavation and imported sand fill

182

Recovery of profit — omission of detention ponds

183

Fill and re-grading

183

Variations

183

Petit Morne Value

186

Cedar Hill Value

186

Insurance and performance security

186

Other Provisional sums

188

Overheads resulting from the suspension of works

190

Equipment

191

Landslip

192

Clearing and grubbing: IPC1

193

Embankment from borrow

194

The Systemically Defective Nature of Namalco's Works — Defective Work — Bill Section C

196

Interest

197

SECTION TWO

The Ancillary Claim

198

Disposition

199

Costs

201

Picton Project

201

Cedar Hill Project

202

Contractual obligations/breaches under common law duty

209

Monthly progress reports

212

Provisional sums

221

Embankment from borrow

222

Roopsingh Road Contract

225

Provisional sums

226

Equipment

226

Recovery of profit — omission of detention ponds

231

Fill and re-grading

234

Variations

235

Petit Morne Contract

236

The Petit Morne Project calculations

236

Sub-standard and defective works

238

Overheads

238

Equipment

240

Wrongful variation to excavation widths

241

Recovery of profit — omission of detention ponds

242

Assessment of Interest

242

AASHTO 180/191

242

The Counterclaim of APCL to the Ancillary Claim

243

INTRODUCTION
1

To say that this case has been somewhat of a challenge would be to underestimate the sheer volume of issues and sub-issues which have been raised. Contrary to the assertion of the Attorneys at Law for the Claimant that it was really a simple matter, its complexity has literally consumed a disproportionate amount of the court's time and resources despite the efforts of the court to minimise that occurrence. In that regard, the court has also intentionally refrained from setting out all of the evidence; as so to do would be to detract from what the court hopes the reader would find to be more interesting and comprehensible than burdensome. That is not to say that the court has not considered all of the evidence that was presented before it as it has. The court has, however, tried to keep the decision within the limits of the reasonable.

2

The nature of the case has presented considerable overlap between the Claim and the Ancillary Claim both in terms of facts and law. To that end, where an issue may not have been dealt with as fully as the court would have liked to treat with it in one area, it has more likely than not been dealt with in the other area. Additionally, having regard to the myriad of findings the court has attempted to make appropriate orders for relief as best suits the case. As with all judgments the longer it lives with the writer the more he wishes he could add to his writing but there comes a time when it must end and the judgment delivered.

3

The court wishes to add that rarely does a court mention the word “politics” in a judgment and for very good reasons, the most important of which is the preservation of the independence of the Judiciary. However, it will not escape the reader that these claims and those similar to them have been the subject of much speculation on all sides of the political fence if one is to accept that which is printed in the newspaper. The courts have never been and ought never to be involved in the business of politics so that the findings made herein are devoid of any such consideration for the absolute avoidance of doubt. It is necessary to remind our people of this steadfast principle from time to time in order to maintain the confidence reposed in the courts throughout our twin island Republic.

OVERVIEW
4

The Claimant (“Namalco”) and the Defendant (“EMBD”, a state enterprise) entered into contracts for six (6) construction projects at Mahaica, Brickfield, Cedar Hill, Roopsingh Road, Petit Morne and Picton Monkey Town under which Namalco was to perform infrastructural...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT